SEQENS – Villeneuve la Garenne (FR)
Project :
Setting up of a new production process reserved for the production of a new High Potent Active Pharmatical Ingredient production :
. Workshop N°1 Dismantling, rearrangement of the existing workshop into a new production unit with ISO7/8 – Safebridge 3B containment,
. Workshop N°2 : Setting up of a new washing unit and expansion in the existing chemical workshop to set up new reactors
Assignments : EPCm contract
. Basic design, FEED, detailed engineering studies
. Procurement
. Assistance for work construction orders
. VISA of construction studies
. Supervision of construction
. Assistance for completions, Qualification assistance
INGENICA thanks SEQENS for its trust.