AFYREN NEOXY – Saint Avold (FR)
`
Project : Construction of a new green chemical plant in the Carling chemical plant area (57-France).
. Production of several types of acid from vegetables fermentation.
. Construction of a complete new plant
. 43,000 hours of studies in 24 months
. 230,000 hours of work in 16 months of construction
. 250 main equipment plus packages – 8km of piping – 300t of framework – Installed power 6.5MW – 2,000 I/O
. Investment amount €61M
Assignments : EPCm contract
. Basic and detailed engineering studies all disciplines,
. Consultation files and order files for construction and supplies,
. VISA mission and follow-up of suppliers and construction studies
. Cost control
. Management of the construction to mechanical completion and start-up
. Construction site safety management
. Start-up process support
INGENICA thanks AFYREN NEOXY for its trust.